Eswatini Inflation Rises to 3.4% as Fuel Costs Jump

October prices rose 0.9% month on month, with liquid fuels and electricity among the biggest annual pressures.
A proposed E987m BADEA loan is part of the total but still awaits parliamentary approval.

The financing plan for the first phase of the Mkhondvo-Ngwavuma Water Augmentation Project totals E6.060 billion, according to a November 19 breakdown that EWADE provided to the Times of Eswatini. One component — a proposed E987 million BADEA loan — still requires parliamentary approval.
The figures allocate E2.629 billion to Mpakeni Dam, E2.084 billion to the Main Conveyance System, E360 million to secondary distribution, infield distribution and on-farm works in Maloma I and II, and E987 million to the secondary distribution system serving St Philips and Mconcwane/Mcathuvane. Those four amounts add to E6.060 billion.
African Development Bank documents confirm that Phase 1B covers the main conveyance, secondary distribution and on-farm systems intended to supply about 4,600 hectares, complementing the Mpakeni Dam works. The E6.06 billion figure is therefore a current Phase I financing breakdown, not the final cost of the wider multi-phase programme.
Media: Times of Eswatini
Prepared with AI assistance; sources linked below.
Published 20 Nov 2026, 16:05 CAT
Suggest a correction
October prices rose 0.9% month on month, with liquid fuels and electricity among the biggest annual pressures.
The proposal covers online registration, beneficial ownership and tighter rules for closing companies.

The five-country review includes Eswatini. The appraisal and project register use different project-end dates.